SPOST 2
Chatham County's SPLOST 2 started in 1993 and was collected through 1998. This SPLOST focused primarily on the Savannah Trade and Convention Center, with over $84 million dedicated to the project through SPLOST. Additionally, $9 million went to drainage projects countywide, and the first funds were set aside for the Mighty Eighth Air Force Museum.
SPLOST 2 Projects
Project | Type | Amount | GDOT Costs | Status | Complete Date |
---|---|---|---|---|---|
Tybee Pier and Pavilion | Recreation | $2,782,521 | $0 | Completed | |
L. Scott Stell Park | Recreation | $2,638,548 | $0 | In Progress | |
Youth Football - Soldier Field and AMBUC improvements | Recreation | $81,529 | $0 | Completed | |
Jimmy Deloach Parkway, Phase II | Roads | $3,303,954 | $0 | Completed | |
Administrative Annex and Police Headquarters | Other | $5,442,539 | $0 | Completed | 01/28/1998 |
Abercorn Widening from Rio Road to Truman Parkway | Roads | $112,765 | ($1) | In Progress | 06/06/2025 |